The uncomfortable facts behind UK F-35 deliveries

The announcement that the UK had ‘accepted’ the final aircraft in its order for 48 F-35Bs did not mean what many thought it did – and 16 aircraft remain in the US, undelivered, undergoing upgrade or maintenance or allocated to test duties. The current UK-based Lightning force is consequently small and handicapped by encompassing aircraft with different configurations and different software standards. Markedly poor availability further complicates the situation.

48th UK F-35B accepted
Senior DE&S personnel pose with the 48th UK F-35B (ZM182/048) at Lockheed Martin’s Fort Worth site in Dallas, Texas, after the formal acceptance of the aircraft. The final three aircraft all remain at the Lockheed Martin factory. The UK MoD’s DE&S organisation announced the completion of UK F-35B ‘deliveries’ on its Facebook page on 29 March 2026. The aircraft was formally accepted on 20 February. (Crown Copyright)
Jon Lake

On 29 March 2026 the Defence Equipment & Support (DE&S) organisation of the UK Ministry of Defence (MoD) made a ‘Proud moment alert’ on its Facebook page, announcing: “We’ve accepted the final Tranche 1 F-35B Lightning, completing delivery of the UK’s first batch of the world’s most advanced fighter jet.”

This was ‘half true’ and may have been accurate in a narrowly legalistic sense, but it left an entirely misleading impression. Some reading the announcement would assume that all 48 of the F-35B Lightning short-take-off/vertical landing (STOVL) Joint Strike Fighters in the UK’s first tranche were now in UK hands – a few even remembering that one aircraft had been written off after an accident on HMS Queen Elizabeth in November 2021. In fact, two aircraft were stranded on the Azores mid-way through their planned delivery flight and three more remain at Lockheed Martin’s Fort Worth factory, ‘accepted’ by the MoD – and presumably triggering payments to Lockheed Martin – but not yet delivered.

The last three aircraft were all ‘accepted’ on the day they made their maiden flights (or the following day), perhaps implying that this was a milestone that has to be achieved before an aircraft can be accepted, maybe without requiring post-test rectification or essential follow-up flights to have been ‘squared away’.

Allowing for the loss and the non-delivered aircraft, one might assume that there would be 42 F-35Bs at RAF Marham, equipping the two frontline squadrons (No 617 Squadron ‘Dambusters’ and No 809 Squadron) as well as the training unit, No 207 Squadron.

However, six aircraft are assigned to the operational evaluation unit: No 17 Test and Evaluation Squadron (17 TES), operating from Edwards Air Force Base (AFB), Naval Air Station (NAS) Patuxent River and Marine Corps Air Station (MCAS) Beaufort. One is at MCAS Cherry Point for upgrade, while four are at the Fleet Readiness Center South East at NAS Jacksonville for Production Asset Inspection Requirement Tier II (PAIR II) corrosion-mitigation inspections. This is a response to what the NAO called “an emerging issue with higher corrosion than expected in maritime environments”.

Four F-35Bs are undergoing PAIR II corrosion-mitigation inspections with the Fleet Readiness Center South East at NAS Jacksonville following the UK’s lengthy CSG25 carrier deployment. This led to an emerging issue with higher-than-expected corrosion. (Crown Copyright)

This leaves 23 aircraft at RAF Marham and eight forward deployed to RAF Akrotiri on Cyprus.

Nor are all aircraft to the same standard. Five Marham aircraft (and three at Edwards AFB) are early low-rate initial production (LRIP) jets, originally delivered with Technology Refresh Level 1 (TR1) software and believed to be incapable of being upgraded to TR-3 standards (the entry point and enabler for the coming Block 4 upgrade).

Six aircraft at Marham (and two aircraft assigned to 17 TES) were built with TR3 software and six more (one assigned to 17 TES) have been upgraded to the same standard. Unfortunately, the TR3 programme has been dogged by delays and difficulties, with the initial ‘truncated’ software release (40P01) providing just an “initial training capability”, while the second (40P02) confers only a “more robust combat training capability”. Neither makes the aircraft fully ‘combat-coded’, however, meaning that about 11 UK Lightning Force aircraft are essentially capable of ‘training missions only’.

This means that the UK Lightning Force has about 16 aircraft with TR2 software and five built with TR1. These are believed to be the only fully operational F-35Bs at the moment, though TR1, TR2 and TR3 aircraft all participated in last year’s Carrier Strike Group deployment aboard the aircraft carrier HMS Prince of Wales.

The Block 4 upgrade is not fully defined and has been badly delayed, but does promise to increase F-35 capabilities, not least through the integration of the MBDA Meteor beyond-visual-range air-to-air missile (BVRAAM) and the Spear air-to-surface missile. In 2013 the MoD expected that Block 4 would be fully delivered by 2022 and required Meteor and Spear by 2024, but by 2023 the upgrade was reported to have been delayed until 2029 and the F-35 Joint Program Office (JPO) now expects that Block 4 will not be completely delivered until 2033, with Meteor and Spear entering service “in the mid-2030s”. The MoD now wants to mitigate capability risk by purchasing interim weapons.

Lieutenant Commander Nick Baker flew the first of a series of Meteor captive carry test flights on 20 November 2024 in an F-35B assigned to the US Navy test squadron, VX-23. Several flights were conducted with a specially instrumented Meteor to gather data inside the F-35B’s weapon bay. (US DoD)

A UK National Audit Office (NAO) report on 11 July 2025 revealed that the UK F-35 fleet was available to perform all required missions (the full mission-capable rate) for about one third of the MoD’s target. This represented two-fifths of the global F-35B fleet’s full mission-capable rate. It also revealed that availability to perform at least one of seven possible required missions (a mission-capable rate) was about half of the MoD’s target figure (and three fifths of the global fleet rate). The NAO did not disclose the actual percentages “for national security reasons”. It was stated that UK rates were significantly lower than those of the global F-35B fleet.

This has had an impact on training and the Royal Air Force (RAF) has been unable to reach the modest MoD requirement of flying 10 hours per pilot per month, nor even the reduced requirement of approximately 7.5 hours per month. The RAF has also been operating fewer than the budgeted synthetic training hours.

Given the poor availability of the F-35B, this means that a much smaller number of aircraft would be expected to be ready for operations at any time and that pilots might be inadequately prepared for complex missions.

The programme has cost more than was anticipated it would spend at the time of the 2013 business case. The NAO has estimated that the MoD has spent GBP 11 billion (EUR 12.63 billion) to date on F-35 capability, with an additional GBP 1.5 billion on personnel, infrastructure, training flights, other overheads and earlier sunk costs. The NAO judged that: “In our view, the capability achieved for the estimated GBP 11 billion spent to date is a disappointing return so far.”

The NAO said that the F-35B programme’s whole-life costs are considerably higher than the MoD has publicly reported. A public forecast for whole-life costs of GBP 18.76 billion assumes that only 48 aircraft will be procured and that these will leave service in 2048.

In June 2025 the UK’s Strategic Defence Review (SDR) stated that the UK would require more F-35 aircraft over the coming decade and subsequently announced that it would procure another 27 aircraft between 2030 and 2033, including 15 more STOVL F-35Bs and 12 conventional take-off and landing F-35As. The latter were justified on the basis of their lower unit price and longer endurance for conversion training, but also due to the fact that they would be capable of carrying US-owned nuclear weapons under the NATO Dual Capable Aircraft (DCA) nuclear sharing arrangement.

An F-35 dropping an inert B61-12 nuclear bomb. The UK is to procure another 27 F-35 aircraft between 2030 and 2033, including F-35As. The business case for the F-35A rested on its lower unit price and longer endurance for conversion training, but the variant will also be capable of carrying US-owned B61-13 nuclear weapons under the NATO Dual Capable Aircraft (DCA) nuclear sharing arrangement. (US DoD)

Official MoD policy is still to procure an eventual total of 138 aircraft with an out-of-service date of 2069. This would result in whole-life equipment and support costs of GBP 57 billion – or GBP 71 billion including wider MoD costs such as personnel, fuel and infrastructure.

The UK requirement for 138 aircraft was used to determine the composite share ratio (CSR) paid to the programme, covering each customer nation’s share of the global project administration, sustainment, upgrade and overhead costs. As a result, the UK’s CSR is 4.6%: the second highest in the programme after the US contribution of 81.9%.

The UK was the first partner to join the US in the Joint Strike Fighter project in 1995 and paid 10% of the concept demonstration phase costs (GBP 144 million). In January 2001 the UK committed a further GBP 1.7 billion (USD 2 billion) to become the only ‘Level 1’ partner for the F-35’s system development and demonstration phase to 2020. This Level 1 status allowed input into the design and development of the aircraft and was supposed to guarantee some ‘freedom of action’ in terms of upgrades, support and sustainment.

The upbeat DE&S announcement noted that: “Flying from our Queen Elizabeth-class carriers, these aircraft are a powerful symbol of UK defence capability, today and for decades to come.” Critics suggest that the F-35B may well be symbolic of UK defence capability, in that the true situation is rather less impressive than a superficial impression might suggest. However, whatever the F-35B’s problems, it has been acknowledged that: “The capability provided by the F-35 across its multiple roles is significantly superior to any previous UK aircraft.”

 

UK RAF F-35B status, April 2026
Serial/code Lot/TR Unit Location First flight Notes
ZM135/001 LRIP3/TR1 17 TES Edwards 13/04/2012 Handed over Fort Worth 12/07/2012, deliv’d Eglin 23/07/2012, to Edwards 13/1/2015
ZM136/002 LRIP3/TR1 17 TES Edwards 11/07/2012 Deliv’d Eglin 19/10/2012
ZM137/003 LRIP4/TR1 UKLF1 Marham 01/04/201 Deliv’d Eglin 25/06/2013, to Beaufort 3/02/2015, to Marham 16/07/2019
ZM138/004 LRIP7/TR1 17 TES Edwards 02/12/2015 Deliv’d Patuxent River 08/02/2016
ZM139/005 LRIP8/TR1 UKLF Marham 06/05/2016 Deliv’d Marham 16/07/2019
ZM140/006 LRIP8/TR1 UKLF Marham 23/08/2016 Deliv’d Marham 03/08/2018
ZM141/007 LRIP8/TR1 UKLF1 Marham 28/10/2016 Deliv’d Marham 03/08/2018
ZM142/008 LRIP8/TR1 UKLF Marham 28/10/2016 At Beaufort by 02/2017, deliv’d Marham 03/08/201
ZM143/009 LRIP9/TR2 UKLF Cherry Point 03/03/201 Deliv’d Marham 03/08/2018, reported as last TR-1 jet, perhaps in error. Upgraded to TR3?
ZM144/010 LRIP9/TR2 UKLF1 Akrotiri 04/05/2017 Deliv’d Marham 03/08/2018. Upgraded to TR3?
ZM145/011 LRIP9/TR2 UKLF1 Akrotiri 06/06/2017 Deliv’d Marham 06/06/2018. Upgraded to TR3?
ZM146/012 LRIP9/TR2 UKLF2 Marham 08/08/2017 Deliv’d Beaufort 06/11/2017, to Marham 06/06/2018. Upgraded to TR3?
ZM147/013 LRIP9/TR2 UKLF Marham 10/10/2017 Deliv’d Beaufort 13/11/2017, to Marham 06/06/2018. Upgraded to TR3?
ZM148/014 LRIP9/TR2 UKLF Marham 29/11/2017 Deliv’d Beaufort 14/12/2017, to Marham 06/06/2018
ZM149/015 LRIP10/TR2 UKLF Marham 31/01/2018 Deliv’d Marham 16/07/2019
ZM150/016 LRIP10/TR2 UKLF Akrotiri 08/08/2018 Beaufort by 02/2019, deliv’d to Marham 16/07/2019
ZM151/017 LRIP11/TR2 UKLF Marham 10/10/2018 Deliv’d Beaufort 16/11/2018, to Marham 16/07/201
ZM152/018 LRIP11/TR2 Written off Scrapped 12/06/2019 Deliv’d Marham 16/07/2019, w/o 17/11/2021
ZM153/019 LRIP12/TR2 UKLF1 Jacksonville 08/08/2020 Deliv’d Marham 30/11/2020
ZM154/020 LRIP12/TR2 UKLF Marham 10/10/2020 Deliv’d Marham 30/11/2020
ZM155/021 LRIP12/TR2 UKLF Marham 18/10/2020 Deliv’d Marham 30/11/2020
ZM156/022 LRIP13/TR2 UKLF1 Akrotiri 29/06/2021 Deliv’d Marham 28/10/2021
ZM157/023 LRIP13/TR2 UKLF2 Akrotiri 03/08/2021 Deliv’d Marham 28/10/2021
ZM158/024 LRIP13/TR2 UKLF2 Marham 02/09/2021 Deliv’d Marham 28/10/2021
ZM159/025 LRIP13/TR2 UKLF2 Marham 17/10/2021 Deliv’d Marham 03/03/2022
ZM160/026 LRIP13/TR2 UKLF1 Marham 15/11/2021 Deliv’d Marham 03/03/2022
ZM161/027 LRIP13/TR2 UKLF1 Jacksonville 07/12/2021 Deliv’d Marham 03/03/2022 (reported cost USD 104.8 m)
ZM162/028 LRIP14/TR2 UKLF Marham 04/07/2022 Deliv’d Marham 18/11/2022 (reported cost USD 101.3 m)
ZM163/029 LRIP14/TR2 UKLF2 Jacksonville 16/08/2022 Deliv’d Marham 18/11/2022
ZM164/030 LRIP14/TR2 UKLF1 Akrotiri 13/09/2022 Deliv’d Marham 18/11/2022
ZM165/031 LRIP14/TR2 17 TES Edwards 03/03/2023 Deliv’d Edwards 21/06/2023 (first TR-3 aircraft?)
ZM166/032 LRIP14/TR2 UKLF Marham 04/04/2023 Deliv’d Marham 22/06/2023
ZM167/033 LRIP14/TR2 UKLF1 Jacksonville 11/04/2023 Deliv’d Marham 22/06/2023
ZM168/034 LRIP14/TR2 UKLF2 Akrotiri 18/09/2023 Deliv’d Marham 16/03/2024
ZM169/035 LRIP14/TR2 UKLF Akrotiri 15/10/2023 Deliv’d Marham 16/03/2024
ZM170/036 LRIP15/TR3 17 TES Paxutent River 07/04/2024 Reportedly deliv’d 17/01/2025
ZM171/037 LRIP15/TR3 UKLF Marham 17/03/2024 Deliv’d Marham 04-07/05/2025
ZM172/038 Lot 16/TR3 UKLF Marham 14/04/2025 Deliv’d Marham 04-07/05/2025
ZM173/039 Lot 16/TR3 UKLF Marham 03/05/2025 Deliv’d 18-19/08/2025 via Portsmouth International Airport (former Pease AFB)
ZM174/040 Lot 16/TR3 UKLF Marham 17/05/2025 Deliv’d 18-19/08/2025 via Portsmouth International Airport (former Pease AFB)
ZM175/041 Lot 16/TR3 UKLF Marham 29/05/2025 Deliv’d Marham 22/06/2025
ZM176/042 Lot 17/TR3 17 TES Beaufort 06/11/202 Deliv’d 24/02/2026
ZM177/043 Lot 17/TR3 Lajes 25/11/2025 Left Fort Worth 6/3/26, arrived Lajes c09/03/202
ZM178/044 Lot 17/TR3 UKLF Marham 02/12/2025 Deliv’d Marham 20/03/2026
ZM179/045 Lot 17/TR3 Lajes 09/01/2026 Left Fort Worth 6/3/26, arrived Lajes c09/03/2026
ZM180/046 Lot 17/TR3 Fort Worth 12/02/2026 Accepted at Fort Worth 12/02/2026
ZM181/047 Lot 17/TR3 Fort Worth 06/01/2026 Accepted at Fort Worth 06/01/2026
ZM182/048 Lot 17/TR3 Fort Worth 19/02/2026 Accepted at Fort Worth 20/02/2026
Notes
UKLF = UK Lightning Force
1 Wears ‘617-PWLS’ tail markings
2 Wears ‘809-PWLS’ tail markings
Codes are based on sequential UK build numbers, such that ZM135/001 is build number 2BK.0001 and ZM182/048 is build number 2BK.0048
F-35Bs were painted in a more uniform colour from ZM146

Share post

You may be interested in

Categories

All NewsAir

Used tags

DE&SF-35AF-35BLockheed MartinRoyal Air ForceUKUK MoD

Similar posts